Tasks
-
How to implement duration driven scheduling using the Excel import template
If you don't use Microsoft Project and want to do duration-driven scheduling, you can use the Excel template linked at the bottom of this FAQ to create a task list and import this into PPO. Microsoft Project has some powerful features that make it...
-
How do I map a Yes/No field in the Excel Template?
PPO allows Tasks to be imported from Microsoft Project (MSP) or Microsoft Excel. In certain cases, there is a need to map additional fields on the template that needs to be imported into PPO. Below are the steps to follow when introducing a new Y...
-
How can I capture Baselines and track slippage in PPO?
PPO allows for the capturing of baselines by making use of a Baseline Date field on the project entity, as well as two calculated fields on the tasks entity. Project Stakeholders can track the slippage of the project schedule through the Task Vari...
-
How can the Planned Progress % be recorded in MSP / PPO?
Step 1 - Implement Number1 Field Open your Microsoft Project (MSP) plan and implement a new column called: Number1. Once the column is added, right-click on the column heading and select the Custom Fields option.Click on the Formula button. Then...
-
How can I import tasks without using Microsoft Project?
Not everyone has access to Microsoft Project in order to create their project schedules. As an alternative, PPO supports imports using Microsoft Excel, Google Sheets, and Excel for Mac. For the above, you can follow this link to access and use the...
-
Is my task duration calculated if I’m not using MSP?
The answer is Yes. The task Duration field is a hidden field that is calculated in the back end of PPO. Background: In Microsoft Project, the task duration is calculated when creating your project schedules. When those schedules are imported into...
-
How does PPO calculate planned and actual progress percentages on a project level?
PPO calculates the overall planned and actual progress percentages of your project. These calculations provide an accurate, calculated view of the advancement of a project without relying on the project managers to import their schedules on a regu...
-
How can I import resources from MSP directly into PPO?
PPO’s Resources entity maintains a pool of resources that is used by PPO users to allocate Issues, Risks, Tasks, and other related items. When Microsoft Project (MSP) is used for project planning and the project plan is then imported into PPO, res...
-
What is the MSP Add-In and how do I install it?
The Microsoft Project Add-In for PPO (MSP Add-In) is an add-in / plugin for Microsoft Project that allows you to update your MSP schedule based on information in PPO, e.g. you have updated your actual progress on the tasks in PPO and now want to s...
-
How can I update my MSP plan with information from PPO using the MSP Add-in?
The MSP Add-in After the latest version of the MSP Add-in has been downloaded and installed (see this FAQ) follow these steps to update your MSP plan with information from PPO.It is important to note that the Update from PPO functionality will onl...
-
Does re-importing my project plan overwrite the existing Tasks in the Tasks section and how does it work?
PPO does not overwrite project plans When a project plan is re-imported into PPO, PPO compares the information in its database with that provided by MSP and updates the Tasks accordingly. PPO does not overwrite the Tasks in the Tasks section, it f...
-
What are the common problems associated with MSP and how can I fix them?
PPO's bi-directional integration with MSP allows for data to be transferred quickly and easily from MSP to PPO and back to MSP. However, as with any integration, there are some basic problems or errors that present themselves from time to time. Th...
-
How can I assign multiple responsible people to a single Task in PPO like I can in Microsoft Project?
This cannot be done in PPO. This is not a PPO shortcoming or lack of functionality but is based on the principle (best practice) of holding a single person responsible / accountable for a piece of work (whether it is a Task, Issue or Risk).Microso...
-
How can I show the phase of a Task in my MSP schedule?
Step 1 - Implement a Phase Data FieldA new data field must be added to the Tasks entity as follows: Note: when the field is added the Field Type must be Custom List and must be linked to a custom list containing all the required Project Phases. S...