When creating a new task after the scheduler had been finalised. The default date for that new task becomes the start date of the project. I would like to put forth an idea to have the new task date to be defaulted to the current date

Date
Votes
1 comment
-
Guy Jelley Official comment Thank you Nomathamsanqa for your idea.
We have completed this. Please note it works as follows now:
- If you add a new task under the Project Task the start date will be set to today.
- If you add a task under a Summary Task the start date will be the day after the end date of the last task under that Summary Task.
- If you add a new task under an existing Task, thus making the existing task a New Summary Task, the start date of the new task will be the same as the Start Date of the new Summary Task.
- If you add a new task after a normal task, thus not making the normal task a Summary task, the new task will have a start date of the day after the normal task it follows.