Allow more and less than 100% Allocation on Tasks

PPO allows you to import a Project Plan successfully where two resources (each with 100 % allocation) are assigned to one task.  

Once imported to PPO, the task is only assigned to the first resource on the MSP plan and reflects a 200% Allocation as it adds the two resources Allocation % together.

When a user then tries to edit the task however, it does not allow you to submit, as the Allocation % is more than 100%. 

The following error message is received:  Allocation % is a % field (1-100 allowed)

We suggest that this default functionality be amended to allow values greater than 100 to be captured through the front end of PPO.

The way the Allocation % is set up currently  does not make sense as a resource is able to work more than 100% of their Standard Working Hours.  

 

 