Allow multiple resources on group tasks

I agree with the scheduling best practice of only allocating a single resource to a task so that when imported to PPO then it allocates the task to a single resource for completion. However, in the case of group tasks such as project meetings and workshops, it is unwieldy to create a separate task for every resource for the meeting, especially if it is a weekly progress meeting that all 20 team members attend every week. Can you not allow a task such as this to have multiple resources allocated and maybe tag it as a special task type in MS Project using a custom text field that can be mapped to PPO?