Follow

Task Reports

This article provides detailed explanations of the Task Reports available in PPO:

Task Detail Report

The report includes all the fields on the Task entity for all task records and projects. If the “Include Project Information” checkbox is selected, the report will also include all the fields on the project entity.

Task_Detail_Report.jpg

Task Progress Report

The report focuses on the planned and actual progress of all the tasks on the project. It shows the progress as reflected in the project schedules once imported into PPO and also the individual progress updates on the tasks.

Task_Progress_Report.jpg

Task Variance Report

The aim of this report is to show the variance between the baseline start and end dates and the current planned start and end dates.

The baseline start date and baseline end date are calculated by storing the planned start date and planned end date respectively of the first task record imported/added (i.e. the first history record). Alternatively, the baseline start and end dates can be calculated on the Tasks entity, making use of a baseline date field on the Projects entity. For more information on this alternative, see the following FAQ.

kb_reports_taskvariance.png 

Tasks Not Completed Report

This report shows tasks where the planned end date has passed, but the task has not been completed (actual progress percentage is not 100%).

Tasks_Not_Completed_Report.jpg

Milestone Certificate

The Milestone Certificate is available from a link on the Task >> View page.

Link_to_the_Milestone_Certificate.jpg

The report shows all the fields on the Tasks entity as well as an Approvals section where the Project Sponsor, Project Owner and Project Manager can provide sign off on the milestone.

Milestone_Certificate.jpg

Upcoming Tasks Report

The tasks that appear on this report are determined by the task relevance period. These reports and dashboards use the task relevance period setting to determine which tasks to display. If the configuration setting is set to 30 days the reports will show all tasks that begin or are due within the next 30 days ignoring tasks further down the line.

For full details on how the task relevance period impacts the Upcoming Tasks Report, see the following FAQ.

Upcoming_Tasks_Report.jpg

 

Was this article helpful?
3 out of 3 found this helpful
Have more questions? Submit a request
Article is closed for comments.
Start a 30 Day Free TrialClick ClickNo Credit Card and No Obligation
Powered by Zendesk