How can I show the Critical Path of the schedule in PPO?

Step 1 - Implement Critical Path Data Field
A new data field must be added to the Tasks entity as follows:

critical_path.gif

Note: when the field is added the Field Type must be Yes/No and the List Criteria must be Ticked.

Step 2 - Map the MSP Critical Path field to PPO
The critical path is determined in Microsoft Project (MSP) automatically and the field in MSP is called "critical":

msp_critical.gif


In order for this field to be imported into PPO the MSP field needs to be mapped to the PPO field on the Task Import Field under the System Configuration:

T20_taskcritical.gif

Note: in the example above the PPO field is T20 and the MSP field is taskcritical.

Step 3 - Import the Project Plan into PPO
Import your Microsoft Project (MSP) plan into PPO. The Critical field from MSP will be imported into the PPO Data Field:

critical_path_mapping.gif

Step 4 - View Critical Path
The Critical Path can now be viewed from the Task List page:

critical_path_on_Task_list.gif

or, by creating a filter using the Critical Path Data Field:

filter.gif

 

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request
Article is closed for comments.
Start a 30 Day Free TrialClick ClickNo Credit Card and No Obligation
Powered by Zendesk